Key Takeaways
Write the business case before you shop for square feet
Start with the trigger. A data center move may begin with an expiring lease, rising costs, a consolidation, inadequate capacity, or unacceptable disaster risk. Each trigger changes the project: a lease deadline affects both the move and the return of the old space, while a disaster-recovery gap may require greater distance between sites. The book’s central advice is to define the business need before approaching vendors, rather than starting with a room size or a preferred building.
Turn needs into specifications. Gather current and projected space, power, network, availability, and location requirements in terms operators can answer. This first book in a five-book series focuses on that translation. Clear requirements let site selection compare like with like, expose expensive tradeoffs, and prevent a vendor’s standard offering from quietly becoming the company’s design.
This is a form of disciplined problem definition: teams make better choices when they distinguish the reason for a project from the solution they happen to be considering. A lease deadline, for example, is a constraint, not proof that renewal or relocation is best. The book also implicitly treats requirements as a shared language between IT, facilities, finance, and vendors. That matters because each group can use the same word, such as availability, to mean something different. The useful caution is that requirements should be ranked, not merely accumulated. An unprioritized wish list can make every option look like a failure.
Match infrastructure resilience to the cost of an outage
Know what tiers certify. The Uptime Institute’s Tier Classification System describes increasing levels of data center infrastructure resilience. Tier 1 has basic, nonredundant infrastructure. Tier 2 adds spare capacity components but retains a single distribution path. Tier 3 supports planned maintenance without interrupting IT, while remaining exposed to some unplanned failures. Tier 4 uses independent, active paths designed to tolerate a single infrastructure fault.
Separate design from uptime. Certification can validate design documents and a constructed facility, but the tier describes infrastructure topology, not the availability of every application running inside. The book notes that a resilient facility cannot compensate for an application that lacks its own recovery design. The right tier depends on the business impact and tolerable duration of an outage, balanced against the substantially higher cost of redundancy.
The tier model is valuable because it replaces vague claims of being highly available with a vocabulary about maintenance and failure behavior. It also exposes a common systems error: reliability at one layer does not automatically propagate upward. A fault-tolerant building can house a fragile application, just as a robust application can be undermined by a single power path. The model is most useful when paired with concrete failure scenarios, such as a failed component during planned maintenance. A tier label alone can still conceal operational practices, dependencies, and recovery gaps that determine real business continuity.
Trace utility power to substations, not merely building entrances
Two cables can share one failure. Operators may advertise dual utility feeds, yet both feeds could originate at one substation or converge through a single switch or transformer. The book groups utility delivery into four power-feed classes, from a single source to a fully redundant arrangement. Its strongest case, Class 4, uses two substations and separate feeds connected so either can support the facility, with the data center controlling and maintaining key equipment.
Ask about the whole path. Redundancy is meaningful only when it reaches beyond the building wall: ask where feeds originate, whether they share routes, and where they converge. The same principle applies inside the facility. In a 2N design, two independent power systems each have capacity for the full load, extending through separate distribution paths toward the IT equipment.
This is the reliability-engineering distinction between duplication and independence. Two components do not protect against a common-cause failure if they share a route, control point, or source. The book’s focus on utility architecture is especially practical because a customer may inspect visible equipment yet have little visibility into the upstream grid. It is reasonable to favor physical diversity, but no arrangement can remove all shared risks, including regional disasters. A useful evaluation therefore asks not only whether paths are separate, but which hazards could still disable both and how long backup operation can last.
Compare the power bill, not just the lease price
Billing can reverse the bargain. Data center power costs combine the electricity used by IT equipment with charges for facility systems such as cooling and electrical losses. The book favors metered billing over circuit-based billing, which charges for a circuit’s full capacity whether or not the customer uses it. One client paid more than $40,000 monthly for power circuits serving 15 cabinet positions; after moving to a metered site, its bill fell below $2,000 per month.
Price the full equation. Compare the utility’s cost per kilowatt-hour, the operator’s power upcharge, and its Power Usage Effectiveness, or PUE. PUE is total facility power divided by IT equipment power. More efficient facilities generally use less extra power, but a low PUE does not guarantee the lowest bill if local electricity costs are high. The meaningful comparison is total operating cost, not one attractive line in a proposal.
This example shows why procurement should use lifecycle cost rather than headline price. A facility is a bundle of space, electricity, cooling, connectivity, and service charges, and the least expensive component can distract from the largest recurring expense. The distinction between metered and circuit billing is also a question of who carries utilization risk: circuit billing shifts it to the customer. PUE helps describe facility overhead, but comparisons require consistent measurement boundaries and billing formulas. Buyers should request both the metric and the actual contract calculation rather than treating one efficiency number as a complete cost forecast.
Treat cooling, airflow, and liquid placement as uptime requirements
Heat needs a path out. Most power consumed by IT equipment becomes heat, so cooling design must remove it and deliver air at conditions compatible with the equipment. Ask where temperature and humidity are measured, which ASHRAE guidance the operator follows, and what redundancy supports cooling. Unlike power, cooling may fail briefly before room temperatures threaten equipment, but that buffer is limited.
Keep air where it belongs. Blank spaces in cabinets, tangled cables, and uncontrolled mixing of hot exhaust with cold supply can undermine cooling. Higher-density equipment may require targeted airflow, containment, or local cooling. A cautionary story in the book describes a failed pump seal that released coolant into a data center, raising the room temperature to 140 degrees. The team had to move systems immediately because the organization lacked adequate disaster-recovery capacity. Separating liquid-bearing equipment from IT space can reduce this exposure.
Cooling is not simply a facilities concern; cabinet layout and cable practices affect whether the engineered system works as intended. This is a useful example of the difference between design reliability and operational reliability. A room can have redundant cooling machinery while poor airflow creates local hot spots. The pump incident also illustrates how a low-probability physical failure can become a business crisis when recovery plans are weak. Still, avoiding liquid near IT equipment is a risk-reduction choice, not a guarantee against water damage; site reviews should consider leaks, drainage, and the consequences of losing cooling as well.
Count usable rack units, then reserve at least 25% for growth
Inventory before estimating. Count the equipment that will actually move, its rack-unit height, and the power it needs. Remove obsolete “zombie” servers, meaning devices that no longer perform a useful function, and consider whether systems can be virtualized before relocation. Separate unusually power-dense equipment, such as blade servers or core network switches, because it may need dedicated cabinets even when it occupies relatively few rack units.
Size for the future, not just day one. Convert the remaining equipment inventory into cabinet positions, then estimate the floor area needed for aisles, infrastructure, and work space. The book recommends at least 25% extra space for growth in environments that are not static. One example turns 60 initial cabinet positions into a planning target of 75. More cabinets are not automatically better: density, power, cooling, access, and the cost of unused capacity must all fit together.
The inventory method reduces a complex space forecast to observable units, but it wisely treats equipment count and power density as different constraints. A rack can have empty vertical space yet be full electrically or thermally. Removing obsolete hardware is also a rare planning opportunity to avoid moving yesterday’s mistakes into tomorrow’s expensive facility. The 25% reserve is a practical buffer, not a universal forecast. Rapidly changing workloads, cloud adoption, or shrinking systems could make it excessive, while growth beyond the historical pattern could make it inadequate. The estimate should be tested against plausible scenarios, not treated as prophecy.
Choose distance and terrain for disasters, not just commute convenience
Avoid shared hazards. A disaster-recovery site must be far enough from the primary site to avoid the same event. The book gives 30 to 50 miles as a minimum rule of thumb, while noting that greater distance can complicate synchronous data replication. Evaluate flood exposure, utility and network reliability, nearby hazards, emergency access, and the other tenants that may attract unwanted attention.
Judge the surroundings, not just the building. A facility may remain dry while flooding blocks every road needed to reach it. The book recounts Hurricane Sandy flooding lower levels of a Manhattan building, damaging generator fuel systems and electrical infrastructure; another protected facility stayed dry but became inaccessible when surrounding streets flooded. Security also depends on setback, vehicle barriers, controlled access, and keeping equipment rooms away from exterior walls and windows. Resilience is a property of the site and its surroundings together.
This is a strong application of geographic risk analysis: a protected building is not resilient if its people, fuel, roads, or utilities are exposed to the same event. The paired flood stories make the distinction between asset protection and operational accessibility tangible. Distance, however, is only a proxy for independence. Two sites can be far apart yet share critical network or utility dependencies, while a nearer site may have genuinely separate infrastructure. Site assessments are strongest when they map specific hazards and dependencies rather than treating mileage, flood-zone labels, or security hardware as conclusive answers.
Treat network access as a site cost and a schedule risk
Inventory every circuit. Before choosing a site, list the carriers and services needed for data, voice, market information, and other traffic. Check whether each provider is already present, how circuits enter the building, whether routes are diverse, and how much latency applications can tolerate. A facility with a low rent may become costly if circuits are expensive or slow to provision.
Look beneath the provider name. Type-2 Service means a provider delivers service using another carrier’s infrastructure. It can make an otherwise unavailable provider possible, but it may add cost, complicate fault resolution, and erase network diversity if both supposedly separate circuits depend on the same underlying route. Ask how long cross-connects take, what they cost to install, and whether monthly fees apply. The author treats carrier provisioning as a recurring source of delay and frustration, so it belongs in the project plan from the start.
The network discussion corrects a common boundary mistake: connectivity is often treated as an IT detail after the real-estate decision, even though it can determine whether a location is viable. Type-2 service makes the distinction between a commercial provider and a physically independent network especially important. This resembles supply-chain risk: different brands may rely on the same underlying asset. Buyers should map routes and escalation responsibilities, not merely collect carrier logos. The book’s frustration with carriers is understandable, but schedule risk can be reduced by early orders, clear ownership, and realistic assumptions rather than by relying on vendor assurances.
Verify round-the-clock operations, fire protection, and support before signing
A facility needs people and procedures. For an unmanned environment, Smart Hands are on-demand technical services that can handle tasks such as installing equipment or checking a connection. Confirm their skills, rates, and availability, along with 24-hour security, loading-dock access, shipping procedures, response-time commitments, and measured service-level performance. A move may require overnight staffing and incur charges outside normal operating hours.
Inspect what happens in an emergency. Ask which fire-suppression system is installed, how detection and alarms work, and how staff exit before an agent is released. Large colocation sites often use pre-action water systems, while gaseous suppression may require enclosed customer spaces. The book also warns against treating application cutover as project completion: returning the old facility, meeting lease conditions, and disposing of equipment can take time and money. Include those tasks in the plan and budget from the outset.
These details reveal that resilience is partly a service relationship, not just an engineering diagram. A technically sound facility can still frustrate a customer if staff cannot access a loading dock at night or support tickets languish. Asking for actual service results is more informative than accepting a contractual promise. Fire protection presents a genuine tradeoff: gaseous systems can limit equipment damage but are not practical in every shared space, while water systems introduce different risks. The broader lesson is to evaluate procedures, incentives, and recovery responsibilities alongside hardware, including the obligations that remain after the new site is live.
Analysis
This book treats data center planning as a translation problem. Business concerns such as downtime, lease deadlines, growth, and disaster exposure must become requirements that a facility operator can answer. The translation is demanding because the same broad claim, especially “redundant” or “available,” can describe very different physical arrangements. The book’s most useful habit is therefore to ask what a promise means in the actual path from utility source to equipment, and in the actual contract from power billing to support response.
Its strongest examples expose hidden dependencies. Two utility feeds can share a substation. A protected building can be stranded by flooded roads. A facility with ample floor area can lack sufficient power or cooling for dense equipment. An efficient site can still cost more if electricity is expensive or billing rules punish low utilization. These are not isolated technical details; they are reminders that the object being evaluated is a whole operating system, including infrastructure, geography, vendors, people, and commercial terms. The book is especially valuable to IT leaders who may know their systems but have limited experience with electrical engineering, cooling, or colocation contracts. It gives them questions to ask without pretending that they should replace the specialist designing the equipment. Its recommendations are strongest as screening rules and negotiation prompts, not universal laws. For example, preferred distances, tier levels, power redundancy, or growth reserves depend on application architecture, replication limits, budget, and risk tolerance. A sophisticated decision process should rank requirements, identify shared failure modes, and model total cost over time.
The narrative also makes a broader point about project completion: migration is not finished when applications run in the new room. The old site must be decommissioned, contracts satisfied, and assets handled. The book’s practical value lies in insisting that these less glamorous tasks belong in the original definition of the project, before deadlines and vendor assumptions narrow the available choices.
Glossary
Tier Classification System
Infrastructure resilience levelsThe Uptime Institute framework classifying data center site infrastructure into four levels. Tier 1 describes basic, nonredundant infrastructure; Tier 2 adds redundant capacity components; Tier 3 supports concurrent maintenance; and Tier 4 is designed to tolerate a single infrastructure fault. The classification concerns physical infrastructure topology, not the availability of applications hosted there.
Data Center Power Feed Classifications
Four utility-feed architecturesThe book's four-part classification for utility power delivery to a data center. It ranges from a single feed and substation, through arrangements with dual feeds or substations, to a fully redundant design with independent sources and paths. The classification helps distinguish genuine power-source diversity from multiple connections that may still share a critical failure point.
2N
Two full independent systemsA redundancy arrangement in which the complete set of required components and distribution paths is duplicated. Each side is designed to carry the full IT load, so one side can remain available if the other fails or is taken out of service. Its value depends on the paths being genuinely independent rather than sharing vulnerable components.
Power Usage Effectiveness (PUE)
Facility power per IT powerA ratio comparing total data center facility power with power consumed by IT equipment. A PUE closer to 1 indicates that less additional power is used for cooling, lighting, and other facility functions. PUE is an efficiency measure, not a complete cost measure: local electricity prices and the operator's billing method also affect the customer's bill.
Type-2 Service
Service using another carrier's networkA network service in which a provider reaches a data center using another carrier's infrastructure, often through an interconnection at a carrier facility. It can provide access where the named provider has no nearby physical network. However, it may undermine route diversity, add complexity to troubleshooting, and change the cost or delivery schedule.
Smart Hands
On-demand technical assistanceA colocation operator's technical support service for customer equipment. Staff may perform physical tasks such as installing hardware, connecting cables, or checking equipment when the customer has no employee on site. Buyers should clarify which tasks are included, staff availability, skill levels, hourly rates, and whether monthly hour blocks expire when unused.
White Space
Area housing IT equipmentThe data center floor area where customer servers, storage, and network equipment are installed. White space planning includes more than the footprint of cabinets: it must account for aisle access, power and cooling distribution, cable routes, equipment density, and room for maintenance. The book uses cabinet counts and rack units to help estimate the required area.
Zombie Server
Unused but still installed equipmentA server or other device that remains in a data center after its application or useful function has ended. It continues to occupy space, draw power, and produce heat without supporting an active need. Identifying and removing such equipment before relocation reduces the amount of infrastructure that must be moved and supported.